Title Deep Depth TJI 360, 560, and 560D Joist Author Weyerhaeuser Subject Provides installation instructions for Keywords “joist, TJI, framing, floor, roof, floor Created Date 3/2/2015 5:35:09 PM
How many TJI joists are in a TJI roof?
®210 TJi ®230 •TJi ®360 TJi ®560 JoiSTS Featuring Trus Joist®TJi®Joists for Floor and Roof applications WoodBYWY.CoM 1.888.453.8358
What kind of nailing do I need for a TJI 560?
TJI®JOIST FLOOR FRAMING Shear transfer nailing: At minimum, use connections equivalent to floor panel nailing schedule For TJI®360 and 560 joists, use one 8d (0.113″ x 2½”) nail each side. Drive nails at an angle at least 1½” from end.
When to use double beveled bearing plate for TJI?
Double beveled bearing plate when slope exceeds. 1⁄4″ in 12″. For TJI ® joists with slopes of 10/12 to 12/12, the vertical depth at bearing will require 11⁄4″ TimberStrand LSL or iLevel® 11⁄8″ rim board (for shear blocking) that is one size deeper than the TJI® joist. TJI® joist flange must bear fully on plate .
Title Deep Depth TJI 360, 560, and 560D Joist Author Weyerhaeuser Subject Provides installation instructions for Keywords “joist, TJI, framing, floor, roof, floor Created Date 3/2/2015 5:35:09 PM
Can a triple TJI joist be used for a perpendicular member?
When supporting a perpendicular member, a triple TJI ® joist may be used. However, it is recommended to avoid such applications due to the complicated attachment requirements. See Technical Bulletin on 3 ply joists TB-820 for additional information.
When to shift TJI joist at bearing plumbing drop?
TJI®JOIST NAILING REqUIREMENTS AT BEARING Plumbing drop Additional joist is required if floor panel edge is unsupported or if span rating is exceeded. Joist may be shifted up to 3″ if floor panel edge is supported and span rating is not exceeded. Do not cut joist flanges. TJI®joist floor framing does not require bridging or mid-span blocking
TJI®JOIST FLOOR FRAMING Shear transfer nailing: At minimum, use connections equivalent to floor panel nailing schedule For TJI®360 and 560 joists, use one 8d (0.113″ x 2½”) nail each side. Drive nails at an angle at least 1½” from end.